Posted by: Patricia Salkin | December 6, 2020

CA Appeals Court Holds When Land is Governed by Both a Vesting Tentative Map and a Subsequent Development Agreement and the Terms Conflict, the Development Agreement Controls

This summary appears in the Perkins Coie Land Use and Development Law Briefing and is posted with permission of the California Land Use Attorneys with Perkins Coie, LLP

North Murrieta Community, LLC, is the master developer of a large community in Riverside County called the “Golden City Project.” In 1999, the City of Murrieta approved a two-year Vesting Tentative Map for a subset of the overall project property. In 2001, four months before the Vesting Tentative Map was set to expire, North Murrieta and the City entered into a Development Agreement, which covered the entire project, including the tract subject to the 1999 Vesting Tentative Map.

The Development Agreement extended the Vesting Tentative Map for fifteen years, locking in regulations and fees for the same period, although now with an effective date of 2001. Importantly, in addition to the new effective date, the City expressly reserved rights in the Development Agreement to impose additional fees (or increase fees) in t future for city-wide impacts that were not fully mitigated at the the time of project approval. The Vesting Tentative Map and Development agreement were both subsequently extended, with final expiration dates of 2019 and 2021, respectively.

In 2003, the City passed a new transportation fee and imposed it on development within the Golden City Project. North Murrieta sued, seeking a refund of the fees on the ground that the Vesting Tentative Map and Development Agreement prohibited imposition of the fees.

The appellate court held that although rights under a vesting tentative map may be extended beyond their normal term through a subsequent development agreement, the terms of the development agreement control. “Vesting tentative maps,” it said, do not impart “a species of super rights that cannot be negotiated away [in a development agreement].”

Here, when North Murrieta and the City negotiated the Development Agreement in 2001, they also negotiated the long-term extension of the Vesting Tentative Map, allowing North Murrieta to retain those rights for several additional years. However, the terms of the Development Agreement made clear that the City did not extend all rights conveyed by the original Vesting Tentative Map. The Development Agreement expressly allowed new, generally-applied fees for impacts not fully mitigated as of its effective date. The Development Agreement was a contract, the court noted, just like any other, and both parties had the opportunity to negotiate the terms. North Murrieta explicitly agreed to modify its rights under the Vesting Tentative Map when it entered into the Development Agreement.

When the stated rights conflicted, the terms of the Development Agreement controlled.

North Murrieta Community, LLC v City of Murrieta, 50 Cal. App. 5th 31 (2020)


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

Categories

%d bloggers like this: